LG Energy Solution Poland (Wroclaw)
- 501, 601, 701 Utility Pipe Hookup work for line No. 8~24
- 301 Utility Pipe Hookup work for line No. 25
- 401 Utility Pipe Hookup work for line No. 5~7
- 401 Machine room pipe work for cold water & steam line
- 501 Notching expansion work (Pipe for water and CDA)
- 401 Roof top duct work for air conditioning improvement
- 401 Vertical Type AHUs + Outdoor units Assembly and Delivery work
- 401 Machine room pipe work for cold water & steam line
- 601 Air Handing Unit Assembly and Delivery work
- 701 Air Handing Unit Assembly and Delivery work
- 301 Air Handing Unit Assembly and Delivery work
- 401 Coater room air conditioning improvement work
- 101 High temperature aging room extension work
- P4 welfare 1,2 building Ourhome utility construction work
- P4 formation building S&I EHP/DHU /PAC delivery & installation work
- 201/401 Duct & Piping Installation of Mixing Chamber Unit
- P3 Utility 1,2 building CDA Pipe Hook-up work
- P4 hook up Work (2022)
- P4 hook up Work (2023)
SK hi-tech battery materials Poland (Dąbrowa Górnicza)
- LIBS Project Equipment installation work
- Equipment installation (Boiler)
- Equipment installation (ORU)
- Heavy equipment installation (chimney)
- Boiler piping installation
- Pump & utility pipe line installation work
SK Innovation Hungary (Komárom)
- Installation of GTS 500 Turbo Chiller
- Clean/Dry room Inspector service
SK Innovation Hungary (SK On Iváncsa Factory)
- Condensing units delivery & installation
- RTU delivery & installation